European Ports Without Shore-Side Electricity (SSE/OPS) — Status and Plans as of 2026

07/28/2026

A survey of European ports that, as of 2026, have not yet applied/used Shore-Side Electricity (SSE), Onshore Power Supply (OPS), Alternative Maritime Power (AMP), High-Voltage Shore Connection (HVSC), or “cold ironing” — but are planning, tendering, or building it.


1. Why this list exists now: the regulatory driver

Two overlapping EU laws are forcing the issue:

  • AFIR (Alternative Fuels Infrastructure Regulation, EU 2023/1804) — requires TEN-T core and comprehensive maritime ports to install OPS at berths handling large container and passenger/cruise ships, largely by 31 December 2029.
  • FuelEU Maritime (EU 2023/1805) — from 1 January 2030, container and passenger ships over 5,000 GT must connect to and use OPS (or an equivalent zero-emission technology) at quaysides in TEN-T ports; from 1 January 2035 this extends to any EU port that already has OPS installed.

Independent audits (DNV for Transport & Environment, July 2025; TT Club, Jan 2026) found that only around 20% of the OPS connections required by 2030 are installed or contracted EU-wide, and that of 31 major ports studied, only four (Algeciras, Livorno, Świnoujście, Valletta) had more than half of what they need. Cruise terminals are further along (~38%) than container terminals (~11%). This means the great majority of European ports — including many very large ones — are still in the “planning/tendering/construction” phase rather than operating SSE.

The list below groups ports by sea region. For each, it gives: current status, what is planned, target dates, and funding source where known. “Comprehensive” here means as broad a cross-section as available reporting allows (major TEN-T ports plus notable secondary/island/cruise ports); it is not an exhaustive inventory of every harbour in Europe, since hundreds of small ports have no public OPS roadmap at all.


2. Western Mediterranean — Italy

Italy has probably the largest and most detailed national pipeline, backed by the National Recovery and Resilience Plan (PNRR): around €700 million (some sources cite €400m PNRR + a further ~€570m in EU-approved state aid running to 2033) targeting at least 15 cold-ironing installations across ~10–50 TEN-T ports.

Port Status (2026) Plan / Target Notes
Genoa No operational SSE at cruise/ferry terminals €26m project (with Savona) for cruise/ferry berths; executive design underway Co-financed by EIB (~€300m loan across a €789m modernization package); contractor Nidec ASI
Savona Not yet operational Cold-ironing converter for cruise port, one ship at a time Same contract/timeline as Genoa, ~2–3 years to completion
Naples Partial/planned Cavotec awarded ~€3m order (March 2026) for shore power systems Part of wider PNRR cold-ironing rollout
Civitavecchia (Rome’s port) Not yet operational Included in national cold-ironing plan; feasibility/design phase Major cruise hub, large XL-class ship traffic
Gioia Tauro Early-stage PNRR-funded electrification project launched Italy’s largest transshipment container hub
La Spezia Early-stage PNRR-funded project launched Also site of Muggiano shipyards test installations
Bari Early-stage PNRR-funded project launched; new cruise terminal also planned (~2026 Adriatic investment package)
Taranto Early-stage PNRR-funded project launched
Venice Partial One of few ports (per DNV/T&E study) with contracted connections for at least one ship segment, but not all Further cold-ironing investment earmarked in 2026 Adriatic funding package (~€252m Italy-wide)
Ravenna Not yet operational Cold-ironing project included in 2026 Adriatic investment package

Livorno is a partial exception — it already has 12–45 MW of shore-power capacity for cruise ships (since 2015/2018) — but its Darsena Europa expansion (due late 2026) is adding a third berth with new shore-power capability, so it remains a live “planning/expansion” case relevant to this list.


3. Western Mediterranean — Spain

Spain’s state port authority (Puertos del Estado) has approved roughly €950 million–€1.6 billion for dock electrification/OPS across the national port system, with €280 million earmarked in the 2026 budget alone (up from 13% to 17.5% of investment share).

Port Status (2026) Plan / Target Notes
Algeciras Partial — largest single OPS deployment planned in the state system Passenger-terminal OPS tendered (~€150,000, Next Generation EU funded); part of broader €40m electrical-supply upgrade Already a leader in installed capacity for some segments, but full cruise/container coverage still pending
Valencia Not yet operational Project under execution One of Spain’s “big three” ports by tonnage
Bilbao Not yet operational Project under execution
Pasaia Not yet operational Project under execution
Vigo Not yet operational Project under execution
Alicante Not yet operational Project under execution
Balearic Islands ports (various) Not yet operational Multiple projects under execution Palma de Mallorca already has 2 ferry connections operational; other Balearic ports still pending
Tarragona Not yet operational Sustainability-linked investment approved for 2026
Ceuta Not yet operational No dedicated OPS project publicly confirmed yet

Barcelona and Cádiz (Bay of Cádiz) have made real progress (Barcelona: 219 ferry OPS connections completed by April 2026, container-terminal OPS at BEST terminal; Cádiz: Spain’s first state-system cruise-ship OPS connection, inaugurated March 2026) but both are flagged by the DNV/T&E study as still lagging behind their 2030 targets for the cruise segment specifically — i.e., partially electrified, not yet fully compliant.


4. Western Mediterranean — France

Port Status (2026) Plan / Target Notes
Dunkerque Not yet operational (per DNV/T&E study) No confirmed installation/contract found in study Flagged among ports “lagging” on 2030 targets
Le Havre Partial Enough connection points contracted for at least one ship segment (cruise), not all; new terminals 2 & 3 OPS due mid/late 2026 Studies began 2018, ahead of regulation
Rouen Not yet operational for the maritime OPS mandate (exempt under current AFIR scope) but has cruise OPS in progress Enough connection points for cruise segment per DNV data One of 3 ports (with Ghent, Terneuzen) not covered by the maritime OPS mandate itself

Marseille-Fos is a rare full success story (three simultaneous cruise-ship OPS connections activated April 2026, 108 MW capacity, 100% renewable) and is included here only for contrast — it is not on the “still needs to build it” list.


5. Eastern Mediterranean / Adriatic — Greece

Greece’s Ministry of Maritime Affairs, working with HEDNO (grid operator) and funded partly via the Connecting Europe Facility (CEF), has a €585 million Port Upgrade Plan targeting cold ironing at 23 ports by 2029. Virtually the entire Greek port system is currently without OPS and in the feasibility/tender stage.

Port Status (2026) Plan / Target Notes
Piraeus Not yet operational Nine berths identified as suitable; FEED studies underway (CIPORT project) for four cruise-vessel OPS positions Aim: transform into a “Green Cruise Hub”; target by end of decade
Thessaloniki Not yet operational Feasibility study completed; progress/barriers outlined Feb 2026 Greece’s second major port
Igoumenitsa Not yet operational €8.9m tender for 3 shore-power points (2×3MW, 1×0.5MW); completion targeted December 2026 One of the more mature pilot projects
Rafina Not yet operational 4 supply points (1.5 MW each) planned; tender expected Early pilot alongside Igoumenitsa
Lavrio Not yet operational Advanced plans presented at a February 2026 conference
Volos Not yet operational Feasibility study completed
Heraklion (Crete) Not yet operational Feasibility study completed
Patras Not yet operational Targeted for cold ironing by 2029
Elefsina Not yet operational Targeted for cold ironing by 2029
Kavala Not yet operational Feasibility study in preparation
Kalamata Not yet operational Targeted for cold ironing by 2029
Katakolo Not yet operational Targeted for cold ironing by 2029
Corfu Not yet operational Feasibility study in preparation
Mykonos Not yet operational Targeted by 2029; major cruise/tourism destination
Mytilene (Lesbos) Not yet operational Targeted by 2029
Naxos Not yet operational Targeted by 2029
Paros Not yet operational Targeted by 2029
Skyros Not yet operational Targeted by 2029
Syros Not yet operational Targeted by 2029
Chios Not yet operational Targeted by 2029
Chania (Crete) Not yet operational Targeted by 2029
Santorini Not yet operational Named in the twelve-port electrification initiative Extremely high cruise-call volumes; strong candidate for early priority
Rhodes Not yet operational Named in the twelve-port electrification initiative

Note: Killini is the exception — the EU-funded Elemed project (with Cyprus’s Limassol and Slovenia’s Koper) delivered the first operational Eastern-Mediterranean OPS connection there.


6. Adriatic — Croatia

Academic case studies (2023) found no concrete cold-ironing implementation plans yet existed for Croatia’s state-owned ports, though experts confirmed strong future feasibility and shipowner interest.

Port Status (2026) Plan / Target Notes
Dubrovnik Not operational No confirmed installation date; studied for HVSC feasibility (15 MVA required) High cruise-ship interest (excursion boats, nautical tourism vessels)
Split Not operational €17m ferry-terminal expansion investment (2026); interest from RoPax/RoRo and cruise segments
Rijeka Not operational Feasibility studied (7.5 MVA required); Croatia positioning itself as an energy/goods transit hub
Šibenik Not operational €8m cruise-hub terminal upgrade allocated (2026); cruise-line interest confirmed
Zadar Not operational Interest from excursion/nautical tourism vessel segment
Ploče Not operational Interest from container-vessel operators; flagged in DNV/T&E study as a non-responding/lagging port

7. Iberian Atlantic — Portugal

Port Status (2026) Plan / Target Notes
Lisbon No investment made yet (confirmed by Reuters/T&E, July 2025) Multi-million-euro cable-laying project to connect port to a power station; targeted for readiness by 2029 One of Europe’s busiest cruise ports — a high-priority gap
Oporto–Leixões Status unclear/non-responsive to DNV survey No public OPS project confirmed Flagged among ports that did not respond to the 2025 EU-wide survey

8. North Sea / Low Countries

Port Status (2026) Plan / Target Notes
Antwerp (Antwerp-Bruges) No investment made yet in seagoing-vessel OPS (per T&E, July 2025), though RoRo short-sea berths have shore power Antwerp Euroterminal (AET) first seagoing-vessel shore-power connection expected operational 2026 Pledged carbon neutrality by 2050; part of North Sea Ports alliance with Ghent/Zeeland
Ghent Not covered by the maritime OPS mandate itself (like Rouen, Terneuzen) but developing infrastructure New electric-truck charging hub opened March 2026; broader electrification program with Netherlands
Rotterdam Partial — flagged as “lagging” for 2030 targets despite a 2025 cruise-terminal shore-power opening Shore Power Roadmap targets full coverage for deep-sea container and cruise terminals by 2028; €90m EIB loan (March 2026) for further development Europe’s largest port by cargo volume

9. Baltic Sea

Port Status (2026) Plan / Target Notes
Gdańsk (Poland) No investment made yet (confirmed by T&E, July 2025) No confirmed public timeline found Major container/LNG hub
Gdynia (Poland) Non-responsive to 2025 EU survey; no confirmed OPS project Status unclear
Tallinn (Estonia) Non-responsive to 2025 EU survey Status unclear
Riga (Latvia) Included in the DNV study’s detailed port sample; no OPS confirmed operational Under review as part of EU-wide OPS gap analysis
Helsinki (Finland) Non-responsive to 2025 EU survey Status unclear
Copenhagen/Malmö (Denmark/Sweden, joint port) Non-responsive to 2025 EU survey Status unclear
Helsingborg (Sweden) Non-responsive to 2025 EU survey Status unclear

Świnoujście (Poland) is a partial exception — it is one of only four ports EU-wide with more than half its required OPS connections installed/contracted — but is listed for context, not as a “still to build” case. Klaipėda (Lithuania) similarly has partial coverage for at least one ship segment.


10. Black Sea

Port Status (2026) Plan / Target Notes
Constanța (Romania) Not yet operational Project to install cold ironing/OPS started (per Ports Europe, March 2026) Romania’s principal Black Sea port
Varna (Bulgaria) Non-responsive to 2025 EU survey; no confirmed OPS project Status unclear
Burgas (Bulgaria) No confirmed public OPS project Status unclear Not directly surveyed but comparable profile to Varna

11. Eastern Mediterranean islands / small states — Cyprus and Malta

Port Status (2026) Plan / Target Notes
Limassol (Cyprus) Non-responsive to 2025 EU survey; had role in Elemed pilot project Regulatory framework for cold ironing developed via Elemed, but full operational OPS not yet confirmed
Marsaxlokk (Malta) Non-responsive to 2025 EU survey Status unclear Major transshipment hub

Valletta (Malta) is again a partial exception — one of the four EU ports with more than half its required connections installed/contracted — included here only for regional context.


12. United Kingdom (non-EU, but subject to comparable domestic pressure)

A dedicated DNV/T&E study of UK ports (2025) found that Southampton is the only UK port among those studied with any contracted/installed OPS, and even that installation (two high-voltage cruise connection points) can only serve one ship at a time due to National Grid capacity constraints, with no further connection points currently planned.

Port Status (2026) Plan / Target Notes
Dover Not operational (only small-scale industrial plugs, outside OPS scope) Mapping energy demand and grid-upgrade needs — an early planning step
Belfast Not operational Mapping funding opportunities
Thames ports (London Gateway/Tilbury area) Not operational Mapping energy demand
Milford Haven Not operational (small-scale industrial plugs only) Mapping grid-upgrade needs
Heysham Not operational Proposed as starting point for UK’s first green shipping corridor (NatPower Marine initiative)

13. Ireland

Port Status (2026) Plan / Target Notes
Dublin No investment made yet (confirmed by T&E, July 2025) No confirmed public OPS timeline; port focus currently on Alexandra Basin redevelopment and offshore-wind readiness
Cork (Ringaskiddy) No confirmed OPS project Redevelopment “on track to be offshore-renewable-ready in 2026,” but this refers to wind-energy logistics infrastructure, not ship-to-shore power
Shannon Foynes No confirmed OPS project Under expansion, decarbonisation plans not yet OPS-specific

14. Key caveats

  • This list changes monthly. Several ports named here as “planning” (e.g., Marseille, Cádiz, parts of Barcelona) achieved partial operational status between the July 2025 audit and mid-2026 — underscoring how fast-moving this space is.
  • “Not applied SSE” does not always mean zero electrification. Many ports have small-scale, low-voltage shore connections for repair yards, tugs, or fishing vessels; the gap discussed here is specifically the high-voltage OPS required for seagoing container, cruise, and passenger ships under AFIR/FuelEU Maritime.
  • Grid capacity, not just port investment, is often the bottleneck. In the UK, Spain, and elsewhere, national electricity-grid upgrades (which can take 5–15 years for permitting and construction) are frequently cited as the limiting factor rather than port-side willingness.
  • Costs are substantial: OPS installation runs roughly €200,000–€6 million per berth, excluding an estimated €584 billion in EU-wide grid upgrades needed to support full rollout.

Sources consulted (selected)

  • Transport & Environment / DNV, European ports unplugged: The state of shore power infrastructure (July 2025) and underlying DNV study (incl. UK ports annex)
  • TT Club shore-power analysis (via Bunker Index, Jan 2026)
  • European Commission — AFIR (Regulation 2023/1804) and FuelEU Maritime (Regulation 2023/1805) official pages
  • Ports Europe (PortSEurope) country/subject news feeds — Italy, Greece, Spain, Croatia, Romania, France, Belgium, Netherlands
  • Port authority and national program announcements (Puertos del Estado, HEDNO/Greek Ministry of Maritime Affairs, Italian PNRR cold-ironing plan, Port of Barcelona/Rotterdam/Marseille-Fos)
  • Academic case studies on Croatian ports (MDPI Sustainability, 2023) and Spanish legal framework (ResearchGate, 2025)